New designs for the $1 billion Greenville Downtown Redevelopment have been unveiled as the project’s site work continues.
RocaPoint Partners, the developer leading the project, presented several new renderings at the city of Greenville’s project preview meeting on April 22. Atlanta-based Dynamik Design serves as the architect for the project.
Phil Mays, a principal at RocaPoint Partners, said they have been coordinating with the city on the project’s architectural design since the beginning of 2024.
“We have been meeting regularly to progress concepts for each building,” Mays said. “It has been a collaborative process, and we appreciate the city’s partnership.”
Building designs
The 40-acre development along University Ridge will feature a mix of commercial, office and residential buildings. Anju Philip, an associate principal at Dynamik Design, explained that the building’s designs range from contemporary to more traditional, drawing inspiration from Greenville’s Main Street.
Two new multifamily buildings were presented at the project preview meeting. Mays explained that the final designs for the buildings are still under development.
“RocaPoint is working closely with architects, the city and the county during the design process, and we are eager to share more details once they are finalized,” Mays said.
The first residential building would be constructed on the north side of University Ridge near the Greenville County Square offices. The seven-story structure will include approximately 180 multifamily units and ground-floor commercial space.
A second multifamily building located on the south side of University Ridge would rise six stories tall. Five floors will house approximately 270 residential units above one story of ground-floor retail.
The city’s Planning Department staff will review the final development plans for both buildings before the developer submits for permitting. According to the city, the building’s final development plans won’t go before the city’s Design Review Board because of the Greenville County Square Sub-District established in 2020. The sub-district outlines architectural and design guidelines, land-use requirements and other development provisions for the project.
Updated renderings for confirmed retail tenants were also on display at the project preview meeting, including Whole Foods, Sports & Social, MOA Korean BBQ and The Perch Kitchen & Tap.
“We currently have 23 national, first-to-market or local favorite tenants signed onto the project, and we are in discussions with several other exciting brands,” Mays said.
Making progress
The design process for the new public parking garage planned in Greenville’s West End is currently underway. Mays said construction is expected to be completed by spring 2026.
Greenville City Council approved a development agreement with RocaPoint Partners to build the 400-space parking garage on Howe Street at the beginning of 2025. The city will allocate $13.38 million for the project.
In addition, a 1.5-acre parcel on the redevelopment site recently went under contract with Charlotte-based Copper Builders LLC. Mays explained that 46 townhomes will be constructed on the property.
Site work and roadway reconfiguration for the redevelopment project have also been underway for the last several months. Mays said the road reconfiguration work is expected to be completed this year.
“A notable milestone was the closure of a portion of University Ridge, which coincided with the opening of the newly constructed Claussen Avenue,” Mays said. “This new roadway configuration has greatly improved traffic flow at the intersection of Howe Street and Harris Street.”
The water lines, sanitary sewer lines, stormwater facilities and underground duct banks for power and fiber cables are currently being installed on the construction site. All site work is expected to be complete by the end of 2025.