Recap: August Planning Commission Meeting
First, thank you for all of the feedback on the Greenville DRB meeting recap in the Aug. 14 UBJ. We decided to just do it and see if it works, and it did. You all seemed to appreciate the additional insight into our public process on proposed projects. Let’s keep that momentum with a recap of last week’s (Aug. 20) Greenville Planning Commission meeting.
The PC wasn’t affected as much as the Design Review Board in the recent shuffle of members, with Meg Terry as the only new member at the meeting. PC meetings work the same as DRB meetings; for each application the board hears a statement from city staff regarding the project, along with their recommendation. Then, they hear from the applicant (if he/she wants to speak). After that, it’s open to public input – both for and against the project.
Once public comment is closed, the board discusses the project, asks the applicant any additional questions and then votes. The only real difference is the area of the city. The PC handles anything outside the Central Business District and historic districts, but still within the city of Greenville limits. It also reviews all new subdivisions along with making recommendations to City Council on zoning and annexation issues.
Gone till September
This month’s agenda was fairly light with only six items, and two of those were postponed. An application to rezone a property on Earle Street from single-family residential to OD, Office and Institutional, was postponed until the September meeting because a required neighborhood meeting wasn’t held. An application for an amendment to the Planned Development at the Greenville Water System’s development was also postponed until September because public notice was not completed.
New zoning classifications
But the PC did have some work to do. The city filed its own application to create three new single-family zoning classifications. R-4: 4,000 sq. ft. minimum lot size; R-15: 15,000 sq. ft. minimum lot size; and R-20: 20,000 sq. ft. minimum lot size.
City personnel asked the PC to table the R-4 request until they look at it more closely. The PC approved the other two unanimously. The city also submitted a text amendment to clarify inconsistencies and to revise the maximum height of accessory structures, front, rear and side setbacks and fences and wall height. This was also approved.
Perry Place
The PC then heard an application from MS Jenkins Building Solutions regarding a subdivision called Perry Place of 0.94 acres located at 99 N. Leach St. and Perry Avenue, seeking to expand from four lots into six lots. The parcel is zoned C2, local commercial. Cheryl and Mike Jenkins, who have rehabbed a lot of houses in Greenville neighborhoods, said they have been working for the past two years on gentrifying bringing new homes to the neighborhood. One of the lots will be green space with picnic tables, which the Jenkins said they hope will bring a sense of community to the area. An existing house, which was already renovated, will become part of the new HOA. A sewer main extension will be needed for the project. The PC approved the project.
New apartments alongside trail?
The bulk of the meeting and discussion concerned the project submitted by JP Hyland for a new 278-unit apartment community on 14 acres along Woodruff Road and the Greenville Health System Swamp Rabbit Trail. The project would be located near the Breakaway Honda dealership. This project had been reviewed informally by the DRB, which said the original design did not meet standards.
The first issue is that the project lacks a secondary access point that would be needed. So the developer, Arlington, Va.-based Bonaventure, was requesting approval on only 199 apartments, saying that if a future access point could be secured, the rest could be built in a second phase.
Bonaventure tweaked the design a bit from the original one reviewed by the DRB, moving some exterior vents to the side instead of the front of the buildings. Brick was added to corner units after the DRB commented that the materials were mostly Hardie Board and they should consider using more masonry and brick. The DRB had also said that the rooflines on the buildings needed to be varied and expressed concern that users of the trail would just see one long building. All in all, even with some modifications to the design, city staff said what was submitted to the PC still wasn’t adequate and recommended denial of the application.
City staff said the developer and architect “still have a ways to go.” Architect Jeff Price, who hails from Liberty, Mo., said he “felt sad that we’re this far apart still.” The developer representative said the developer would continue to work with city staff. It is “100 percent our intent to get where we need to be,” he said.
A question came up about right-of-way access between Bonaventure and GADC to the trail, and the city attorney said he would check into it. A representative from Verdae spoke and said that while “not at all opposed to the project,” Verdae is not willing to give an easement for the secondary access point if the project goes into a second phase.
After more discussion about adding another staircase or connection to the Swamp Rabbit Trail (the project showed one) and additional gables and roofline modifications, the PC decided to table the application until the September meeting and allow city staff, the developer and the architect additional time to make adjustments instead of issuing a denial.
That’s it for this month. Keep the feedback coming, and if you ever have tips, suggestions or concerns, please feel free to reach out to me at sjackson@communityjournals.com.