Starting Jan. 16, the Greenville-Spartanburg Airport District is launching an $18 million multi-phase roadway improvement project to improve traffic flow around the terminal.
The overall project is expected to last 23 months. The initial eight month phase will add an exit lane from Aviation Parkway onto GSP Drive, extend the curbside roadway, and widen GSP Drive.

According to GSP, the project has been broken down into three phases to minimize disruptions to travelers, but some temporary changes in traffic patterns and parking options will be necessary. Visitors will have full access to the airport terminal and parking options throughout the project.
Future phases will include a full reconstruction of the existing curbside roadway and the creation of two new roundabouts on GSP Drive.
Updates on the project will be posted to GSP’s social media channels and through a dedicated web page, gspairport.com/trip.